FIRSTENERGY CORP: FERC Has Yet to Rule on MISO’s June 25 Filing

A decision by the Federal Energy Regulatory Commission on the Midwest Independent Transmission System Operator, Inc.’s (MISO) June 25, 2008 compliance filing is expected this fall of 2008, according to FirstEnergy Corp.’s Form 10-Q dated Aug, 7, 2008.

On Oct. 1,…

FIRSTENERGY CORP: Appeals on FERC Orders Over PJM Rates Pending

The various appeals on the Federal Energy Regulatory Commission’s April 19, 2007 and Jan. 31, 2008 orders regarding the PJM Interconnection L.L.C. transmission rate design are pending in the U.S. Court of Appeals for the Seventh Circuit, according to FirstEnergy…

FIRSTENERGY CORP: FERC Ruling on RPM Buyers’ Complaints Pending

FirstEnergy Corp., in its Form 10-Q dated Aug. 7, 2008, says the Federal Energy Regulatory Commission has yet to rule on a complaint against PJM Interconnection LLC (PJM) relating to Reliability Pricing Model auctions.

On May 30, 2008, a group of…

FIRSTENERGY CORP: Mulls Impact of Duquesne’s Withdrawal from PJM

FirstEnergy Corp. continues to evaluate the impact of Duquesne Light Company’s withdrawal from PJM Interconnection LLC (PJM) on the Company’s operations and financial condition.

On Nov. 8, 2007, Duquesne filed a request with the Federal Energy Regulatory Commission to exit PJM…

FIRSTENERGY CORP: Ameren’s Rehearing Bid v. MISO Tariffs Pending

A rehearing request by Ameren Corp. is pending before the Federal Energy Regulatory Commission, regarding Ameren’s protest to the tariff changes filed by Midwest Independent Transmission System Operator, Inc. (MISO) and majority of its transmission owners.

On Oct. 1, 2003, FirstEnergy…

FIRSTENERGY CORP: TE Mulls FERC Action on Bid v. AMP-Ohio in 3Q

The Toledo Edison Company, an Ohio electric utility operating subsidiary of FirstEnergy Corp., expects the Federal Energy Regulatory Commission to act in the third quarter of 2008, on TE’s requests relating to its interconnection agreement with American Municipal Power-Ohio, Inc.…

FIRSTENERGY CORP: MISO Compliance Filings on ANS Bid Required

The Midwest Independent Transmission System Operator, Inc. (MISO) is required by the Federal Energy Regulatory Commission to make further compliance filings regarding its Ancillary Services Market (ASM) application.

On Oct. 1, 2003, FirstEnergy Corp.’s Ohio transmission facilities were fully integrated into…

FIRSTENERGY CORP: Jan. 2009 Hearings Set for Units’ TSC Filings

Hearings on the Transmission Service Charge filings by FirstEnergy Corp.’s electric utility operating subsidiaries, Metropolitan Edison Company (Met-Ed) and Pennsylvania Electric Company (Penelec), are scheduled to begin in January 2009.

On May 22, 2008, the Pennsylvania Public Utility Commission approved…

FIRSTENERGY CORP: Asks PUCO to Approve MRO Application by Oct.

FirstEnergy Corp.’s Ohio companies have requested the Public Utilities Commission of Ohio to approve the Market Rate Offer application by late October 2008, to allow for the necessary time to conduct the Competitive Bid Process in order for rates to…

FIRSTENERGY: Arguments on Appeal to $16M Award Set for Fall 2008

Oral arguments on Jersey Central Power & Light Company’s appeal to the US$16 million awarded to its bargaining unit employees are expected to take place in the fall of 2008, according to FirstEnergy Corp.’s Form 10-Q dated Aug. 7, 2008.…